Middle Creek DRIVE Rehabilitation
The City of Buda invites you to an in-person neighborhood meeting on Thursday, July 10, 2025 at Buda City Hall to discuss the Middle Creek Drive Rehabilitation Project.
This event offers residents, property owners, and interested community members an opportunity to learn about the project's progress, provide input, and ask questions.
Meeting Details
📅 Date: Thursday, July 10, 2025
🕕 Time: 5:30 PM – 7:00 PM (Drop in anytime)
📍 Location: Buda City Hall, 405 E. Loop St., Buda, TX 78610
If you are unable to attend the in-person meeting, a virtual option will be available below on this webpage from July 10 - July 24. You will be able to view the project plans and leave a comment for the Bond Project Management staff.
project status
Middle Creek Drive Rehabilitation will address ground water and irrigation system infiltration and pavement rehabilitation, including crack sealing, reconstruction, and a thin mill and overlay for portions of the roadway.
Contracted Firm: K Friese + Associate
Current Status:
The City’s geotechnical consultant completed the soil sampling and testing. The geotechnical firm also installed and gathered groundwater data using Piezometers (subsurface water level monitoring equipment) along Middle Creek Drive to monitor, record, and document groundwater levels.
K Friese + Associates has evaluated the collected data and developed a recommendation to rehabilitate Middle Creek Drive. The recommendation includes installing a perforated pipe along the roadway to intercept the groundwater and convey the water to nearby stormwater inlets. The recommendation also includes providing for private connections at property lines – homeowners will have the option to connect from their individual sump pumps through their property to the stormwater connections.
K Friese + Associates presented the recommendations at a Whispering Hollow and public stakeholder meeting on Jan. 17, 2024 at Buda City Hall. A virtual open house was also held for the public’s viewing and comment, view the materials here. Stakeholder input has and will guide the project as it moves through design.
The Buda Bonds Oversight Committee reviewed the Middle Creek Drive project in February 2024 and endorsed the proposed design. City Council reviewed the preliminary design on Mar. 19, 2024. View the Middle Creek Drive City Council presentation here.
The design is currently at the 95% design level and progressing to final plans. Bidding is expected to occur Fall 2025 with construction beginning as early as November 2025 and lasting approximately 8 months. This timeline is subject to change.
A neighborhood meeting is scheduled for Thursday, July 10, 2025.
View Proposed Typical Section for the Middle Creek Drive Rehabilitation project
Bond Amount: $3,800,000